Insulation ball valve installation steps
1, remove the protective cover on both sides of the flange end, in the state of the valve is completely open for flushing cleaning.
2, before installation should be in accordance with the specified signal (electric or gas) for the whole machine test (to prevent vibration due to transportation affect the use of performance), qualified before installation on the line (wiring according to the electric actuator wiring diagram)
3,Before preparing to connect with the pipeline, flush and remove the residual impurities in the pipeline (these substances may damage the valve seat and ball).

4,During installation, do not use the actuator part of the valve as a lifting point for lifting to avoid damage to the actuator and accessories.
5,This type of valve should be installed in the horizontal or vertical direction of the pipeline.
6,The pipeline near the installation point must not have low hanging or bear external force, and pipeline bracket or support can be used to eliminate the deviation of pipeline.
7,After connecting with pipeline, please cross-lock the flange connecting bolts with specified torque.