1, Gate valves are usually connected by flange, and welded connections are also used on special occasions.
2, gate valve can be installed in the horizontal pipeline or vertical pipeline, single and double gate gate valve should be installed in the horizontal pipeline, and the handwheel should be located above the valve, is not allowed to install downwards. Gate valve media flow direction is not restricted.
3, for large diameter and high pressure gate valve, opening and closing torque is larger. In order to reduce the opening and closing torque, can be used to install a bypass valve. Bypass valve is installed in the main gate valve outside, its import and export and the main gate valve on both sides of the practice connection, parallel connection. The main gate valve should be opened before the opening of the bypass valve, into the valve, so that the main gate valve gate before and after the pressure difference is reduced, thereby reducing the main gate valve opening torque. Bypass valve calibre selection should be based on the main valve calibre and use requirements.
4,According to the design installation elevation, mark the vertical centre line of the outlet and the elevation line of the bottom of the gate valve on the wall surface of the outlet, with a deviation of not more than ±10mm, and at the same time, check whether the centre of the lifting hole of the gate body is centred with the hole reserved for the support of the opener;
(1) Lift the gate valve in place, and stand firmly against the solid;
(2) Lift the gate valve into position against the wall, adjust the level and verticality of the gate body (the level and verticality of the bottom groove and side groove of the gate frame is not more than 1/1000), the gate valve frame is reliably connected with the pre-buried steel plate, and the secondary pouring takes effective closure measures to ensure that there is no leakage between the frame of the gate valve and the structure.
(3) Installation of gate valve thrust screw and starter seat, installation level and verticality in accordance with the design requirements, starter centre and gate valve plate screw hole centre should be located in the same vertical line, the verticality deviation is not greater than 1/1000, and the whole process within the deviation is less than 2mm, connecting the gate valve thrust screw to the gate thrust screw plate gate end as a reference, will be adjusted vertically to fix the starter seat of the gate valve thrust screw, starter seat with a padded iron padded solid. The seat of the opener is solidly padded with iron. Then the gate valve and the secondary concrete pouring of the opener.
(4) Gate valve inspection:
① after the installation of the gate valve, check the installation accuracy in line with the installation requirements of the fasteners connected firmly; the grease in the opener to check and refill;
② in the absence of water under the conditions of the gate valve opening and closing test, to achieve flexible operation, action in place, the screw screw smooth, no jamming, jumping, noise phenomenon;
③ In the design water level, the gate valve open and close freely, no jump phenomenon, limit device should be sensitive, accurate and reliable;
④ Assist the supplier to carry out on-site leakage test according to the relevant regulations, under the condition of maximum design water level, the leakage of the gate valve complies with the regulations.